1. Capacity and outside size
The capacity is the inside length times width times depth; one cubic metre is 1,000 litres. The outside length and width add two wall thicknesses.
Using the tool step by step
The numbered marks on the screenshots follow the order in which you use the tool. The fields are filled with an example.

Step 1 Enter your values: dimensions, materials and options. 
Step 2 Read the results: quantities, costs and estimated durations, updated as you type. 
Step 3 Before: the plan of the work to be built, with its dimensions. 
Step 4 After: the 3D rendering of the finished work (an illustration made by the tool, not a photo).
2. Concrete, formwork and excavation
Walls: outside footprint minus inside footprint, times the depth. Floor and cover slab: the outside footprint times their thickness. Formwork covers the inside and outside wall faces and the underside of the cover slab. The excavation is the outside size plus the working space on each side, down to under the blinding.
Worked example: 4 × 3 × 2 m inside, covered tank
Walls and floor 20 cm, cover slab 15 cm, blinding 5 cm, 50 cm working space, 80 kg of steel per m³:
- Capacity 24 m³ = 24,000 litres; outside 4.40 × 3.40 m = 14.96 m².
- Concrete: walls 5.92 + floor 2.992 + cover 2.244 = 11.16 m³; blinding 0.75 m³.
- Formwork: 28 + 31.2 + 12 = 71.2 m².
- Excavation: 5.40 × 4.40 × 2.25 = 53.46 m³.
- Steel: 11.156 × 80 = 892.48 kg; inside lining 40 m².
What this does not cover
The count does not size the walls, check buoyancy or design the reinforcement. The steel ratio is a starting value: replace it with the figure of the engineer’s schedule.
Capacity example: 4 × 3 m inside, 1.5 m deep
Inside volume 4 × 3 × 1.5 = 18 m³, i.e. 18,000 litres (1 m³ = 1,000 L). A tank is never filled to the rim: with the water kept 0.20 m below the edge the useful depth is 1.30 m, so the useful volume is 4 × 3 × 1.30 = 15.6 m³, i.e. 15,600 litres.
Quote the useful capacity to the client, and use the inside dimensions: the wall thickness is added on top of them when you order concrete and formwork.
General information, checked at the date shown. It does not replace advice from a professional for your situation.